JDA is a body constituted under Jaipur Development Authority Act 1982 (Act. 25) under the Department of Urban Development and Housing, Government of Rajasthan. Jaipur Development Authority is responsible for over all development of Jaipur as Jaipur is very fast emerging city in India.. JDA is also responsible to create infrastructure which can meet basic needs of jaipur citizens. Address - Ram Kishor Vyas Bhawan, Indra Circle, Jawaharlal Nehru Marg, Jaipur, Rajasthan 302004 0141 256 9696
Thursday, 5 November 2015
JDA finalize Ambedkar Circle to Sodala Elevated Road Project
Ambedkar Circle to Sodala in 3-4 minutes
After certain alterations, the Jaipur Development Authority (JDA) has finally given green signal for the elevated road between Ambedkar Circle and Sodala Tri-junction, near the existing Bais-Godam Railway over-bridge (ROB).
The project was in limbo for the last two years owing to poor feasibility.
![]() |
| Ambedkar Circle to Sodala elevated road - Phase 2 |
Thursday, 10 September 2015
Monday, 31 August 2015
Water issue between JDA and PHED
PHED – JDA should announce its priorities
JDA – First water should be supplied in buildings.
The government system of water supply seems dice and unable to reach the water needs of various multistory buildings. It seems this problem will not be solved until summers of 2016. Even after tug of word war between JDA and PHED for two months no solution has come to stand. According to PHED, only after declaration of priorities by JDA, DPR can be formed. On other hand JDA puts its issue forward that, they have already explained their trend by multistory high rise buildings, now they cannot foretell their plans of a decade as to how many and how son such projects will be made in future.
Water should reach the old projects -
According to JDC, Shikhar Agarwal, PHED wants to know their future projects. However, this cannot be forecasted as of now. JDA has already clarified the trend set of various multistory building projects that have come up in past decade. PHED should first make water available in all those projects.
Structural cost Rs. 385 sq meters-
Bapu Nagar, Civil Lines, Tilak Nagar and Bani Park was declared multistory zone by PHED. The project based on Delhi water board and Malviya nagar self-finance scheme amounted to structural cost of Rs.385 per square meters on a 10 square km, four multi storied zones.
Water will be available in all multi-storied buildings only after 2017-
The capacity of Bisalpur Dam (surajpura) to Balawala pipeline is 5600 lakh liters only. At present, the city is getting 3950-lakh liters water supply by Bisalpur pipeline. After making a new treatment plant of 2000 lakh liters, another 10 square kms area including Jagatpura, Kho Nagorian, Jamdoli and Prithviraj Nagar would be able to get the water supply. The multistory buildings will only be able to get the water supply by 2017 when the second phase of project of 4000 lakh liters is completed.
Thursday, 27 August 2015
State Hanger Road to Jaipur Airport Terminal 2 Road
Monday, 17 August 2015
PPP Mode Projects in Slow mode
PPP is slow coach in current projects
The work status of the upcoming
20,000 kms road stretch is yet to commence.
The central
government has rejected three proposals under VGF or road viability gap funding
of PPP project. This has
caused concerns for the authorities. Though PWD officials will submit new
proposals for the same. In addition, a meeting is to take place on this matter
between central and state authorities. VGF gets 20% support from central
government and another 20% from state government and rest comes from investors.
If any financial gap is created in this set up then the investor gets benefit
of certain circumstances and monetary help from state government. PPP cell in
PWD department for road development works was formed in September 2014. Earlier
this bill was presented in parliament on 1st August 2014. However,
the governor signed and gave it a green flag on May 2015.
If the circumstances remain same then
only 20% work would be accomplished in the next four years.
The work
order, criteria for selection for work etc has stretched to a year in the PPP
project and the actual work has not yet started. If the present circumstances
do not alter then not even 20% of work would be completed in stipulated time.
Anticipated work/Actual work done-
- 20,000 kms of road is to be completed.
- PWD divided the work in packages. In the first phase of 129 packages, 8910 kms of work is anticipated.
- Out of 129, only eight packages have come under VGF, rest is under annuity. (Annuity - when investor is granted financial support and then it is taken back in form of EMI’s from the investor.)
- Out of this also central government dismissed 3 phases of VGF, as they were not according to central government standards.
- This resulted in no work commenced on any road.
The workflow rate is ok and the
results will be soon visible according to PPP’s SE Mr. Shivlahri Sharma.
According to Mr. Sharma, the workflow is going as anticipated and soon
the results will be visible. All the paperwork has been completed. Now the
roadwork will be seen in full progress. Many challenges are also being faced
like dismissal of three projects by central government. New agendas will be
formed in the next meeting.
Monday, 10 August 2015
First position in water saving - water harvesting and watershed structure
Wednesday, 5 August 2015
JDA will rent upcoming Achrol Golf Course for 60 years
PDKOR
has submitted the project report to Rajasthan Government.
Golf Course to be developed at Achrol, Delhi road on 592 hectares of land
JDA will
give the upcoming gold court at Achrol on rent for 60 years. PDKOR has already
submitted the project report to the state government. The main points of
project development and PPP (Private People Cooperation) have been highlighted
in the report. The project is termed as Golf Court Elide. JDA will soon start the
work order.
This project
speed up on the onset of Resurgent Rajasthan 2015. This has also geared up
the discussion process every few days by the JDA officers. JDC and concerned
officers meeting was held on Friday. Discussions were held upon the PDKOR
report in the meeting. PDKOR is the combined undertaking company of Rajasthan
Government’s Infrastructure leasing and financial services. JDA has handed the
work in progress undertaking to PDKOR for this project.